United Civil was responsible for the civil, cast-in-place concrete foundations, and mechanical support work for a new future separator installation in this live station.

Our detailed scope of work included general site preparations, locating and proofing of existing utilities and removal of a contaminated pipe. Extensive dewatering with stringent environmental oversights were completed before the yard surface could be restored. Cast-in-place foundations included filter separator pedestals, platforms, stairs, pipe supports, truck connection box and bollards. All crane work was considered “Critical Lift” for which we generated detailed work plans over live gas piping and equipment.